Complete this exercise in MSProject. Your project has three dedicated resources: HR Manager, costing $75/hour, HR Analyst, costing $25/hour, and Benefits Coordinator, costing $15/hour. Resource
Complete this exercise in MSProject.
Your project has three dedicated resources: HR Manager, costing $75/hour, HR Analyst, costing $25/hour, and Benefits Coordinator, costing $15/hour. Resource assignments are as shown:
Task | Predecessor | Duration | Resource |
A | - | 2 | HR Manager |
B | - | 7 | HR Analyst |
C | A | 4 | HR Analyst |
D | B, C | 8 | HR Analyst |
E | D | 8 | Benefits Coordinator |
F | D | 6 | Benefits Coordinator |
G | E | 3 | HR Analyst |
H | E, F | 6 | HR Manager |
- Before adding resources, the project takes 29 days. Once resources constraints are entered and leveled, what is the total number of days to complete the project?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started