Complete this exercise in MSProject. Your project has three dedicated resources: HR Manager, costing $75/hour, HR Analyst, costing $25/hour, and Benefits Coordinator, costing $15/hour. Resource

Complete this exercise in MSProject.

Your project has three dedicated resources: HR Manager, costing $75/hour, HR Analyst, costing $25/hour, and Benefits Coordinator, costing $15/hour. Resource assignments are as shown:

Task

Predecessor

Duration

Resource

A

-

2

HR Manager

B

-

7

HR Analyst

C

A

4

HR Analyst

D

B, C

8

HR Analyst

E

D

8

Benefits Coordinator

F

D

6

Benefits Coordinator

G

E

3

HR Analyst

H

E, F

6

HR Manager

  1. Before adding resources, the project takes 29 days. Once resources constraints are entered and leveled, what is the total number of days to complete the project?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quality Management In Construction Projects

Authors: Abdul Razzak Rumane

2nd Edition

0367890038, 978-0367890032

More Books

Students also viewed these General Management questions