Complete this exercise in MSProject. Your project has three dedicated resources: HR Manager, costing $75/hour, HR Analyst, costing $25/hour, and Benefits Coordinator, costing $15/hour. Resource

Complete this exercise in MSProject.

Your project has three dedicated resources: HR Manager, costing $75/hour, HR Analyst, costing $25/hour, and Benefits Coordinator, costing $15/hour. Resource assignments are as shown:

Task

Predecessor

Duration

Resource

A

-

2

HR Manager

B

-

7

HR Analyst

C

A

4

HR Analyst

D

B, C

8

HR Analyst

E

D

8

Benefits Coordinator

F

D

6

Benefits Coordinator

G

E

3

HR Analyst

H

E, F

6

HR Manager

  1. According to the project statistics, what is the planned cost of the project?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quality Management In Construction Projects

Authors: Abdul Razzak Rumane

2nd Edition

0367890038, 978-0367890032

More Books

Students also viewed these General Management questions

Question

If the job involves a client load or caseload, what is it?

Answered: 1 week ago