Complicated Machinery Ltd. manufactures and assembles heavy equipment for industry. It accepted an order from Northern Paper Co. for a large machine that would automate

Complicated Machinery Ltd. manufactures and assembles heavy equipment for industry. It accepted an order from Northern Paper Co. for a large machine that would automate certain processes. A term of the order was that the machine was to be delivered by October 31. The manager of Northern Paper Co. had written in a letter accompanying the offer: "Until the machine is in full operation it is hard to say what our savings will be. A thousand dollars a week is a rough guess."

Complicated Machinery Ltd. failed to deliver until December 26, eight weeks late. It billed Northern Paper Co. for the full price less $8000 (eight weeks at $1000 per week). Northern Paper Co. discovered that the machine actually saved $3000 weekly in production costs. It therefore tendered as payment the full price less $24 000 (eight weeks at $3000 per week). Complicated Machinery Ltd. sued Northern Paper Co.

What is the issue, analysis, remedy for this case?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Law Express Evidence

Authors: Chris Taylor

5th Edition

1292210192, 978-1292210193

More Books

Students also viewed these Law questions

Question

2. Have enough shelves so that materials need not be stacked.

Answered: 1 week ago

Question

3. Im trying to point out what we need to do to make this happen

Answered: 1 week ago