Component Parts B,C,D and E make product A. If component part E has a two week lead time, when should this part be ordered? Product
Component Parts B,C,D and E make product A. If component part E has a two week lead time, when should this part be ordered? Product tree A. When sales demand for item is known B. Before any other parts are ordered C. After Component D is ordered D. Do not order until all parts are available