Question
Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity for Repine Company for September: Standard cost per unit
Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity for Repine Company for September: Standard cost per unit Direct materials 4 units of material A x $ 6.00 per unit
1 unit of material B x $ 8.00 per unit
Direct labor 3 hours x $ 18.00 per hour
Activity for September
Materials purchased
Material A 6,750 units x $ 6.20 per unit
Material B 1,650 units x $ 8.50 per unit
Materials used
Material A 6,225 units
Material B 1,508 units
Direct labor used 4,425 hours x $ 18.80 per hour
Production output 1,500 units
There were no beginning direct materials inventories.
(a) Determine the materials price and quantity variances.
Material A Material B
Materials price variance $Answer Answer F U $Answer Answer F U
Materials quantity variance Answer Answer F U Answer Answer F U
(b) Determine the labor rate and efficiency variances.
Labor rate variance $Answer Answer F U
Labor efficiency variance $Answer Answer F U
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started