Question

1 Approved Answer

Compute expected time for each activity, also variance. Activity o ( optimistic ) p ( pessimistic ) m ( most likely ) Immediate Predecessor te

Compute expected time for each activity, also variance.
Activity
o (optimistic)
p (pessimistic)
m (most likely)
Immediate Predecessor
te (estimated time)
Variance
A
4
6
5
5.0
0.1
B
2
8
5
5.0
1.0
C
5
9
7
A
7.0
0.4
D
4
6
5
A
5.0
0.1
E
2
6
4
B
4.0
0.4
F
3
9
6
B
6.0
1.0
G
10
12
11
C, E
11.0
0.1
H
7
9
8
D,F
8.0
0.1 Determine the probability the project will NOT be finished in 26 days or less?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction To Business Management And General Management

Authors: Don Hellreigel; John Slocum; Susan Jackson

2nd Edition

0190748850, 978-0190748852

More Books

Students also viewed these General Management questions

Question

Understand some techniques for evaluating the HRM function

Answered: 1 week ago