Question
Compute the IRR static for Project E. The appropriate cost of capital is 9 percent. (Do not round intermediate calculations and round your final answer
Compute the IRR static for Project E. The appropriate cost of capital is 9 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.)
Project E
Time: 0 1 2 3 4 5
Cash flow:-$2,900 $910 $900 $800 $580 $380
IRR=______%
Should the project be accepted or rejected?
rejected
accepted
--------------------------------------------------------------------------------------------------------------------------------
Compute the IRR for Project F. The appropriate cost of capital is 12 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.)
Project F
Time: 0 1 2 3 4
Cash flow:-$10,300 $3,950 $4,780 $2,120 $2,750
IRR=_____%
Should the project be accepted or rejected?
Rejected
Accepted
*I tried calculating these problems in excel but I am not sure if I am imputing them in correctly. I know the highlighted stuff is correct.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started