Question
Compute the materials price variance and the quantity variance for the following (you do not have to calculate labor variances): Snazzy Jeans In.c manufactures designer
Compute the materials price variance and the quantity variance for the following (you do not have to calculate labor variances):
Snazzy Jeans In.c manufactures designer jeans. The company uses standard costing nd has developed the following information about standards for its product: Materials- 2 yeards per unit; $10 per yard Labor- .25 DL hour per unit; 11 per hour During October, the company experienced an unanticipated spike in demand and increase production. Although planned production was for 8,000 units, the company actually produced 10,000 units. In anticipation of the original production volume, 18,000 yards were purchased at total cost of $175,000. During the month, 22,000 yards of material were used and 2400 direct labor hours were worked. Direct labor cost for the month totaled $27,000.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started