Compute the NPV for Project M if the appropriate cost of capital is 8 percent. (Negative amount should be indicated by a minus sign. Do
Compute the NPV for Project M if the appropriate cost of capital is 8 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.)
Project M
Time: 0 1 2 3 4 5
Cash flow $2,900 $650 $780 $820 $900 $400
NPV $
Should the project be accepted or rejected?