compute the npv for project x and accept or reject the project with the cash flows shown below if the appropriate cost of capital is
compute the npv for project x and accept or reject the project with the cash flows shown below if the appropriate cost of capital is 10 percent. Cash flows of project x: year 0: -100, Year 1: 50, Year 2: 60, Year 3: 70