Computer Exercises 1 6 . The Planning Department of an electronics firm has set up the activities for development and production of a new MP

Computer Exercises
16. The Planning Department of an electronics firm has set up the activities for development and production of a new MP3 player. Given the following information, develop a project network using Microsoft Project. Assume a five-day workweek and the project starts on January 4,2017.
\table[[Activity ID,Description,Activity Predecessor,Activity Time (weeks)],[1,Staff,None,2],[2,Develop market program,1,3],[3,Select channels of distribution,1,8],[4,Patent,1,12],[5,Pilot production,1,4],[6,Test market,5,4],[7,Ad promotion,2,4],[8,Set up for production,4,6,16]]
The project team has requested that you create a network for the project and determine if the project can be completed in 45 weeks.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Ignite Your Lyfe Self Esteem Through Entrepreneurship

Authors: Jameelah Wilkerson

1st Edition

979-8458529761

More Books

Students also viewed these General Management questions

Question

What is the basic features of Plato soul......?

Answered: 1 week ago

Question

Term also regard to God......?

Answered: 1 week ago

Question

Poetic deals primarily with what genre......?

Answered: 1 week ago

Question

The work we call physics is more properly described what...?

Answered: 1 week ago

Question

Whose niece did Aristotle marry?

Answered: 1 week ago