Computer Project Exercises In developing the exercises, trade-offs had to be made to enrich the learning experience. One of the major problems students initially encounter

Computer Project Exercises

In developing the exercises, trade-offs had to be made to enrich the learning experience. One of the major problems students initially encounter is data and detail overload. This reduces their ability to identify project and data problems and to compare alternatives. Although the project found in the exercises is real, it has been reduced and detail has been eliminated many times to concentrate on applying project management principles and understanding linkages. In addition, other simplifying assumptions have been made so that students and instructors can trace problems and discuss outcomes. These assumptions detract from reality, but they keep the focus on the objectives of the exercises and reduce student frustration with software intricacies. Moving from these exercises to real projects is primarily one of increasing detail. The simplifying assumptions are given below (make sure they are included in “default,” “preferences,” and/or “options” sections of the software used):

The POM + Project*

Big Kola Company has been concerned that specialized fruit drinks have been eroding their cola market. The CEO mandates that “If you can't beat them, join them.” Grape juice was the first product that was successful after an advertising blitz claiming the antitoxin benefits. Lately, competition is compressing grape juice margins and profits. Months of additional market surveys and focus groups have resulted in three potential high-margin drinks: cranberry, blueberry, and pomegranate. All these choices represent antitoxins. The decision is to produce the pomegranate drink that has many health claims. For example, the relative ability of these juices to eliminate harmful free radicals (antitoxins) is 71 percent for pomegranate, 33 percent for blueberry, and 20 percent for cranberry (Technion Institute of Technology). The market potential appears very attractive and should have a higher profit margin than the other potential juice products. Another appeal for pomegranate juice is its familiarity in the Middle East and Asia.

The Priority Matrix for the POM+ Project is:

TimeScopeCost
ConstrainX
EnhanceX
AcceptX

* Cliff Gray, Erik Larson, & Pinyarat Sirisomboonsuk, doctoral candidate at Rawls College of Business, Texas Tech University.

Page 642

Connor Gage, the project manager, has formed his project team and the members have come up with the following work breakdown structure.

1.0 POM+Project

1.1 R&D product development

1.1.1 Need survey

1.1.2 Set product specs

1.1.3 Shelf life report

1.1.4 Nutrition report

1.2 Secure fruit suppliers

1.3 Initial Production

1.3.1 Equipment rehab

1.3.2 Production trials

1.3.3 Quality trials

1.3.4 Quality metrics

1.3.5 Quality training

1.4 Distribution

1.4.1 Market testing

1.4.2 Package design

1.4.3 Select distributors

1.5 Legal

1.5.1 Complete FDA certification

1.5.2 Register trademark

1.6 Prepare product launch

Part 1

Develop the WBS outline using the software available (save your file).

Use this file and the information provided below to create a project schedule.

The following holidays are observed: January 1, Martin Luther King Day (third Monday in January), Memorial Day (last Monday in May), July 4th, Labor Day (first Monday in September), Thanksgiving Day (4th Thursday in November), December 25 and 26.

If a holiday falls on a Saturday then Friday will be given as an extra day off, and if it falls on a Sunday then Monday will be given off.

The project team works eight-hour days, Monday through Friday.

The project will begin on January 3, 2012.

Based on this schedule, submit a memo that answers the following questions:

When is the project estimated to be completed? How many working days will it take?

What is the critical path?

Which activity has the most total slack?

How sensitive is this network?

Identify two sensible milestones and explain your choice.

Page 643

Include the following (one page) printouts:

A Gantt chart.

A network diagram highlighting the critical path.

A schedule table reporting ES, LS, EF, LF, and slack for each activity.

Hints: Change the timescale to months and weeks. The estimated duration of the project is 135 days.

Remember: Save your files for future exercises!

The following information has been derived from the WBS. Note that the activity number is what appears in the software with the complete WBS entered.

#*ActivityDurationPredecessor(s)
 3Need survey20None
 4Set product specs15 3
 5Shelf life report10 4
 6Nutrition report 5 4
 7Select fruit suppliers20 5, 6
 9Equipment rehab30 4
10Production trials15 7, 9
11Quality trials2010
12Quality metrics 511
13Quality training1512
15Market testing30 5, 6
16Package design1515
17Select distributors25 5, 6
19Complete FDA certification15 7, 15
20Register trademark 5 7,15
21Prepare product launch1513, 16, 17, 19FS + 25 days, 20FS + 15 days

FS = Finish to Start lag

Part 2

Remember the old saying, “A project plan is not a schedule until resources are committed.” This exercise illustrates this sometime subtle, but important point.

Using your files from Part 1, input resources and their costs if you have not already done so. All information is found in Tables A2.1 and A2.2.

TABLE A2.1 Resource Assignments

ActivityResources
Need surveyMRKT (500%)
Set product specsR&D (400%), MRKT (200%)
Shelf life reportR&D (300%)
Nutrition reportR&D (300%)
Select fruit suppliersPURCH (100%)
Equipment rehabENG (1,000%), PROD (2,000%)
Production trialsPROD (1,500%), PURCH (100%), ENG (1,000%)
Quality trialsQUAL (300%), PROD (500%)
Quality metricsQUAL (300%), PROD (100%)
Quality trainingQUAL (300%), PROD (1,500%)
Market testingMRKT (500%)
Package designDESIGN (300%), MRKT (100%)
Select distributorsMRKT (500%)
Complete FDA certificationLEGAL (300%)
Register trademarkLEGAL (300%)
Prepare product launchQUAL (300%), PURCH (200%), PROD (1,500%), MRKT (500%), ENG (500%), R&D (100%)

TABLE A2.2 Resources Availability and Pay Rates

ResourceAbbrevAvailableHourly rate
Marketing staffMRKT 5$ 80/hr
R&DR&D 5$ 80/hr
EngineeringENG10$100/hr
PurchasingPURCH 2$ 60/hr
Quality engineersQUAL 3$ 80/hr
DesignersDESIGN 3$ 60/hr
Legal staffLEGAL 3$120/hr
ProductionPROD20$ 60/hr

Prepare a memo that addresses the following questions:

Include a Gantt chart with the schedule table after leveling within slack.

Which if any of the resources are overallocated?

Assume that the project is time constrained and try to resolve any overallocation problems by leveling within slack. What happens?

What is the impact of leveling within slack on the sensitivity of the network?

Assume the project is resource constrained and resolve any overallocation problems by leveling outside of slack. What happens?

Page 644

Include a Gantt chart with the schedule table after leveling outside of slack.

Note: No splitting of activities is allowed.

Note: No partial assignments (e.g., 50 percent). All resources must be assigned 100 percent.

Part 3

Top management has accepted the July 19th completion schedule created at the end of Part 2. Prepare a brief memo that addresses the following questions:

How much will the project cost? What is the most expensive activity?

What does the cash flow statement tell you about how costs are distributed over the life span of the project?

Include a monthly cash flow for the project.

Once you are confident that you have the final schedule, save the file as a baseline. Hint: Save a backup file just in case without baseline!

Page 645

Part 4 A

Assume that today is March 31, 2012, and Table A2.3 contains the tracking information for the project up till now. Enter this information into your saved baseline file and prepare a status report for the first three months of the POM+ project.

TABLE A2.3 Status Report March 31, 2012

ActivityActual StartActual FinishActual DurationRemaining Duration
Need survey1/3/12 2/2/1222 0
Set product specs2/3/122/28/1218 0
Shelf life report 2/29/123/13/1210 0
Nutrition report 3/14/123/19/12 4 0
Equipment rehab 2/29/122312

Your status report should also address the following questions:

How is the project progressing in terms of cost and schedule?

What activities have gone well? What activities have not gone well?

What do the PCIB and PCIC indicate in terms of how much of the project has been accomplished to date?

What is the forecasted cost at completion (EACf)? What is the predicted VACf?

Report and interpret the TCPI for the project at this point in time.

What is the estimated date of completion?

How well is the project doing in terms of its priorities?

Try to present the above information in a form worthy of consideration by top management.

Include an Earned Value table and a Tracking Gantt Chart.

Note: Insert March 31, 2012, as the status date in the Project Information box.

Part 4 B

Assume that today is May 31, 2012, and Table A2.4 contains the tracking information for the project up till now. Enter this information into your saved baseline file and prepare a status report for the POM+ project.

TABLE A2.4 Status Report March 31, 2012

ActivityActual StartActual FinishActual DurationRemaining Duration
Need survey1/3/122/2/1222 0
Set product specs2/3/12 2/28/1218 0
Shelf life report 2/29/12 3/13/1210 0
Nutrition report 3/14/12 3/19/12 4 0
Select fruit suppliers4/3/12 4/30/1220 0
Equipment rehab 2/29/12 4/11/1231 0
Production trials 4/17/125/4/1214 0
Quality trials5/7/12 5/31/1218 0
Market testing4/4/125/9/1226 0
Package design 5/10/12 5/25/1212 0
Select distributors 5/28/12 418
Complete FDA certification 5/11/12 5/31/1214 0

Your status report should address the following questions:

How is the project progressing in terms of cost and schedule?

What activities have gone well? What activities have not gone well?

What do the PCIB and PCIC indicate in terms of how much of the project has been accomplished to date?

What is the forecasted cost at completion (EACf)? What is the predicted VACf?

Report and interpret the TCPI for the project at this point in time.

What is the estimated date of completion?

How well is the project doing in terms of its priorities?

Try to present the above information in a form worthy of consideration by top management.

Include an Earned Value table and a Tracking Gantt Chart.

Note: Insert May 31, 2012, as the status date in the Project Information box.

Step by Step Solution

3.49 Rating (159 Votes )

There are 3 Steps involved in it

Step: 1

Part1 1 Here is how you can develop the WBS outline using Excel Organize the Project Structure Based on the provided WBS organize the project tasks hierarchically For example 10 POM Project 11 RD Prod... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Accounting Information for Decision-Making and Strategy Execution

Authors: Anthony A. Atkinson, Robert S. Kaplan, Ella Mae Matsumura, S. Mark Young

6th Edition

137024975, 978-0137024971

More Books

Students also viewed these General Management questions

Question

(7b-4c-1)-2 (2b3c-2)5 Simplify.

Answered: 1 week ago

Question

What does a capital spending plan do?

Answered: 1 week ago