Consider a bagel store selling three types of bagels that are produced according to the process flow diagram outline below. We assume the demand is

Consider a bagel store selling three types of bagels that are produced according to the process flow diagram outline below. We assume the demand is 180 bagels a day, of which there are 30 grilled veggie, 110 veggie only, and 40 cream cheese. Assume that the workday is 10 hours long and each resource is staffed with one worker.
Moreover, we assume the following Processing times:
Cut Grilled Stuff Veggies Cream Cheese Wrap
Processing Time 3[min/bagel]10[min/bagel]5
[min/bagel]4
[min/bagel]2
[min/bagel]
Processing times are independent of which bagel type is processed at a resource (for example, cutting a bagel takes the same time for a cream cheese bagel as for a veggie bagel).
a. Where in the process is the bottleneck?
b. How many units can the process produce within on hour, assuming the product mix has to remain constant?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Today

Authors: Terri A. Scandura, Kim Gower

1st Edition

1506385877, 978-1506385877

More Books

Students also viewed these General Management questions

Question

What do you need to know about your students to motivate them?

Answered: 1 week ago

Question

7. Identify four antecedents that influence intercultural contact.

Answered: 1 week ago

Question

5. Describe the relationship between history and identity.

Answered: 1 week ago