Question

1 Approved Answer

Consider a project that has an expected completion time of 60 weeks and a standard deviation of five weeks. What is the probability that the

Consider a project that has an expected completion time of 60 weeks and a standard deviation of five weeks. What is the probability that the project is finished in 70 weeks or fewer? (Round to two decimals.)

A. 0.98
B. 0.48
C. 0.50
D. 0.02
E. 0.63

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

A First Course in General Relativity

Authors: Bernard Schutz

2nd edition

521887054, 978-0521887052

More Books

Students also viewed these Mathematics questions

Question

Why do you want to leave your current job?

Answered: 1 week ago