Question
Consider a project whose task XYZ budget is $12,000 with the start date of 5 Dec and end date of 15 Dec, by 11th Dec
Consider a project whose task XYZ budget is $12,000 with the start date of 5 Dec and end date of 15 Dec, by 11th Dec task is supposed to be 60% complete but actual percent completed is 40%. The actual cost of the task A is $4000.
Calculate the following:
- Schedule Variance
- Schedule Performance Index
- Cost Variance
- Cost Performance Index
Step by Step Solution
3.42 Rating (149 Votes )
There are 3 Steps involved in it
Step: 1
To calculate the Schedule Variance SV we can use the formula SV Earned Value EV Planned Value PV whe...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get StartedRecommended Textbook for
Income Tax Fundamentals 2013
Authors: Gerald E. Whittenburg, Martha Altus Buller, Steven L Gill
31st Edition
1111972516, 978-1285586618, 1285586611, 978-1285613109, 978-1111972516
Students also viewed these General Management questions
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
View Answer in SolutionInn App