Consider a real-time system having five tasks. Their period and execution times are given in the following table. Check whether the tasks are RM schedulable
Consider a real-time system having five tasks. Their period and execution times are given in the following table. Check whether the tasks are RM schedulable or not.
Task | Execution Time (e) | Period (p) |
T1 | 20 | 100 |
T2 | 10 | 150 |
T3 | 55 | 110 |
T4 | 40 | 100 |
T5 | 75 | 180 |