Question: Consider a set of 5 periodic tasks with their execution profiles given below. Develop the scheduling diagram of these processes employing EDF. Process Arrival A

Consider a set of 5 periodic tasks with their execution profiles given below. Develop the scheduling diagram of these processes employing EDF. Process Arrival A 10 B 20 D E 60 Burst Time Deadline 20 100 20 25 20 50 20 90 20 75 40 50