Consider a set of five processes P1, P2,P3,P4 and P5 arriving in the order P1, P2, P3,P4 and P5 at time instant 0 and having

Consider a set of five processes P1, P2,P3,P4 and P5 arriving in the order P1, P2, P3,P4 and P5 at time instant 0 and having CPU burst times as shown below. Draw the Gantt chart and calculate the average waiting time, average turnaround time using FCFS and SJF algorithm.

Process

Burst time (ms)

P1

8

P2

6

P3

1

P4

9

P5

3

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Object Databases The Essentials

Authors: Mary E. S. Loomis

1st Edition

020156341X, 978-0201563412

More Books

Students also viewed these Databases questions