Consider activity A Create the Foundation depicted in Figure 2 . According to the calculation for estimated time, activity A should have an expected duration
Consider activity A Create the Foundation depicted in Figure According to the calculation for estimated time, activity A should have an expected duration of how many days?
Activity A Time
Activity Optimistic Time Most Likely Time Pessimistic Time
A Create the Foundation days days days
Group of answer choices
days
days
days
days