Consider an end-item product C with the following master schedule and product structure tree: Week 1 2 3 4 5 6 7 8 9 10

  1. Consider an end-item product C with the following master schedule and product structure tree:

Week 1 2 3 4 5 6 7 8 9 10
Quantity 300 200

A (3) B (2)

(LT=2 wks) (LT=1 wk)

Other important information:

  1. One C is made up of 3 As and 2 Bs.

  1. The assembly of A and B to make C is one week.

  1. The part A is made by the company and lead time is two weeks.

  1. The part B is made by the company and lead time is one week.

  1. C follows a lot-for-lot policy. The company follows a lot-size ordering policy for both A and B with lot size of 80 for A and 40 for B.

  1. There is a scheduled receipt for 50 B at the beginning of week 1.

  1. There are 30 units of C on hand prior to period 1 and 0 units on hand for A and B prior to period 1.

On the next page, explode out the MRP schedule and fill in all cells of the schedule which would have nonzero values

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Responsible Business Operations Challenges And Opportunities

Authors: Jayashankar M Swaminathan, Vinayak Deshpande

1st Edition

3030519562, 978-3030519568

More Books

Students also viewed these General Management questions

Question

What are substitutes and complements?

Answered: 1 week ago