Consider Christine Phillips project involving planning and coordinating next springs sales management training program for her company as described in Prob. 22.2-1. After constructing the

Immediate Estimated Activity Activity Description Predecessors Duration Select location A 2 weeks 3 weeks B Obtain speakers C Make speaker travel plans A, B 2 weeks 2 weeks Prepare and mail brochure A, B 3 weeks Take reservations

Consider Christine Phillip’s project involving planning and coordinating next spring’s sales management training program for her company as described in Prob. 22.2-1. After constructing the project network, she now is ready for the following steps.

(a) Find all the paths and path lengths through this project net- work. Which of these paths is a critical path?

(b) Find the earliest times, latest times, and slack for each activity. Use this information to determine which of the paths is a critical path.

(c) It is now one week later, and Christine is ahead of schedule. She has already selected a location for the sales meeting, and all the other activities are right on schedule. Will this shorten the length of the project? Why or why not?

Immediate Estimated Predecessors Duration Activity Activity Description Select location Obtain speakers Make speaker travel plans Prepare and mail brochure Take reservations A 2 weeks B 3 weeks A, B , 2 weeks 2 weeks E 3 weeks | |

Step by Step Solution

3.33 Rating (168 Votes )

There are 3 Steps involved in it

Step: 1

a The project network paths in terms of predecessor successor relationship and their correspondin... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction to Operations Research

Authors: Frederick S. Hillier, Gerald J. Lieberman

10th edition

978-0072535105, 72535105, 978-1259162985

More Books

Students also viewed these General Management questions

Question

Evaluate the integral, if it exists. Jo y(y + 1) dy

Answered: 1 week ago