The Nelligen Road and Bridge construction entails 27 activities. Create two production sequences for the road section by grouping the road activities within 16-19 work

The Nelligen Road and Bridge construction entails 27 activities. Create two production sequences for the road section by grouping the road activities within 16-19 work packages:

  1. Safety barriers (roads)
  2. Clearing and grubbing 
  3. Soft soil treatment (abutment)
  4. Excavations and concrete line open drains of trenches for open drains
  5. Batter stabilisation (soil nailing)
  6. Signposting 
  7. Base course pavement layer 
  8. SO and SA gutter
  9. Drainage (excavation and installation of pipes, pits and subsoil drains)
  10. Asphalt
  11. Pavement marking
  12. Footpath
  13. Subgrade preparation
  14. Landscaping
  15. Gabion retaining walls
  16. Sprayed bitumen sealing
  17. Erosion and sedimentation control
  18. Pedestrian fencing
  19. Earthworks - cut or fill 
  20. Sub base pavement layer

Produce a line of balance for these activities within the timeframe of 12-24 months. The cycle size, batch size, number of teams, and buffer for the activities are as follows:

ActivitiesDescriptionTeam detailsMonthly (or two fortnights) productivity
AsphaltPlace and compact asphaltic concrete.1 Paving machine, 1 steel roller, 1 rubber tyred roller, 5 workers to control trucks, check levels, control traffic6000m
Base pavement layerPlace and compact imported quarry subbase and level accurately.1 grader, 1 water cart, 1 vibrating steel rollers, rubber tyred roller, 2 workers to check levels and monitor plant1100m
Batter stabilisation (soil nailing)Drill and insert steel bars, grout holesTrack drill, Truck, grout pump 4 workers360m
Clearing and grubbingRemove vegetation, grass and tree roots. Transport to tip.1 Bulldozer, 1 loader, 2 trucks with 12 tonne capacity, 2 workers to assist in setting out, control and direction of plant.1800m
Drainage excavation and installation of pipes, pits & sub soil drainsDrainage- excavation and installation of pipes, pits and subsoil drains1 backhoe, 1 truck, 12 tonne, 4 workers to place pipes and check level1400m
Earthworks cut and fillEarthworks - Cut: Strip and load topsoil, excavate down to top of subgrade, load material and rough trim the top of subgrade.
Earthworks - Fill: Spread fill material dumped by trucks, add moisture to aid proper compaction.
Cut: 1 Excavator, 4 trucks with 12 tonne capacity, 2 workers to assist in setting out, level control and direction of plant.
Fill: 1 grader, 1 water cart, 2 vibrating steel drum rollers, 2 workers to assist in setting out, level control and direction of plant. Use trucks from excavation,
800m
Erosion and sediment controlConstruction of sedimentation basins and surface drainage channels to prevent sediment entering clean watercourses.1 Excavator, 1 truck with 12 tonne capacity, 2 workers to assist in setting out, control and direction of plant.1800m
Excavation and concrete lining of table and catch drainsExcavate and shape to correct level1 excavator, 2 trucks, 4 workers to check and trim levels,  pour and finish concrete1000m
FootpathPour concrete on one side of road plus landscaping of remainder of footpath.1 small excavator, 1 truck, 6 workers to check levels, setup formwork and reinforcing, pour concrete, cure concrete900m
Gabion retaining wallConstruct rock filled, wire gabion wall1 truck with small crane, 1 small backhoe to move rock fill, 4 workers to place rocks, and tie wire baskets together180m
LandscapingLandscaping of medians, footpaths and batter slopes. Spread topsoil, lay turf, and plant trees.1 front end loader to spread soil, 4 workers to lay turf and plant, water and fertilise trees.2600m
Pavement markingPaint line marking, place raised pavement markers1 line marking machine, 6 workers to set out and place pavement markers11000m
Pedestrian fencingConstruct pedestrian fencing at back of footpath1 truck, 4 workers to pour footings and set up fence2600m
PiersSetup formwork, place reinforcement, pour concrete, cure concrete for piers1 crane, 1 barge, 1 pusher barge, 4 workers to check levels, setup bearings, set up formwork, pour and cure concrete2 piers
Safety barriers (road)Install posts for the safety barriers and connect the wire rope barriersBackhoe with post borer, 1 truck, 4 workers to set out and attach barrier rails1700m
SignpostingPour footings, erect structures, mount signs1 truck with small crane, 1 small backhoe for excavation, 4 workers to pour footings, fix signs to structure5800m
SO and SA kerb and gutterSet out levels, place and compact base, pour and finish concrete  gutter.1 Kerbmaker machine, 4 workers, 1 small compactor1800m
Soft soil treatment at esatern abutmentDrill and insert steel tubes, fill with concrete, construct wharf1 Pile boring machine, 1 truck, 4 workers to check levels, place reinforcement, pour concrete.76 piles
Sprayed bitumen sealingSpray bitumen, spread aggregate, roll aggregate.Specialist crew - sprayer, 4 trucks, rubber tyred roller 6 workers6000m
Sub base pavement layerPlace and compact imported quarry subbase in one 300mm layer. Level accurately.1 grader, 1 water cart, 2 vibrating steel rollers, 1 rubber tyred roller,2 workers to check levels1100m
Sub grade preparationAccurately level the top of the excavation or top of fill. Compact to required density.1 grader, 1 water cart, 2 vibrating steel rollers, 1 rubber tyred roller, 2 workers to check levels1400m

     

Step by Step Solution

There are 3 Steps involved in it

Step: 1

SOLUTION Based on the information provided here are two possible production sequences for the road s... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Computer Networking A Top-Down Approach

Authors: James F. Kurose, Keith W. Ross

5th edition

136079679, 978-0136079675

More Books

Students also viewed these Accounting questions