The Nelligen Road and Bridge construction entails 27 activities. Create two production sequences for the road section by grouping the road activities within 16-19 work
The Nelligen Road and Bridge construction entails 27 activities. Create two production sequences for the road section by grouping the road activities within 16-19 work packages:
- Safety barriers (roads)
- Clearing and grubbing
- Soft soil treatment (abutment)
- Excavations and concrete line open drains of trenches for open drains
- Batter stabilisation (soil nailing)
- Signposting
- Base course pavement layer
- SO and SA gutter
- Drainage (excavation and installation of pipes, pits and subsoil drains)
- Asphalt
- Pavement marking
- Footpath
- Subgrade preparation
- Landscaping
- Gabion retaining walls
- Sprayed bitumen sealing
- Erosion and sedimentation control
- Pedestrian fencing
- Earthworks - cut or fill
- Sub base pavement layer
Produce a line of balance for these activities within the timeframe of 12-24 months. The cycle size, batch size, number of teams, and buffer for the activities are as follows:
Activities | Description | Team details | Monthly (or two fortnights) productivity |
Asphalt | Place and compact asphaltic concrete. | 1 Paving machine, 1 steel roller, 1 rubber tyred roller, 5 workers to control trucks, check levels, control traffic | 6000m |
Base pavement layer | Place and compact imported quarry subbase and level accurately. | 1 grader, 1 water cart, 1 vibrating steel rollers, rubber tyred roller, 2 workers to check levels and monitor plant | 1100m |
Batter stabilisation (soil nailing) | Drill and insert steel bars, grout holes | Track drill, Truck, grout pump 4 workers | 360m |
Clearing and grubbing | Remove vegetation, grass and tree roots. Transport to tip. | 1 Bulldozer, 1 loader, 2 trucks with 12 tonne capacity, 2 workers to assist in setting out, control and direction of plant. | 1800m |
Drainage excavation and installation of pipes, pits & sub soil drains | Drainage- excavation and installation of pipes, pits and subsoil drains | 1 backhoe, 1 truck, 12 tonne, 4 workers to place pipes and check level | 1400m |
Earthworks cut and fill | Earthworks - Cut: Strip and load topsoil, excavate down to top of subgrade, load material and rough trim the top of subgrade. Earthworks - Fill: Spread fill material dumped by trucks, add moisture to aid proper compaction. | Cut: 1 Excavator, 4 trucks with 12 tonne capacity, 2 workers to assist in setting out, level control and direction of plant. Fill: 1 grader, 1 water cart, 2 vibrating steel drum rollers, 2 workers to assist in setting out, level control and direction of plant. Use trucks from excavation, | 800m |
Erosion and sediment control | Construction of sedimentation basins and surface drainage channels to prevent sediment entering clean watercourses. | 1 Excavator, 1 truck with 12 tonne capacity, 2 workers to assist in setting out, control and direction of plant. | 1800m |
Excavation and concrete lining of table and catch drains | Excavate and shape to correct level | 1 excavator, 2 trucks, 4 workers to check and trim levels, pour and finish concrete | 1000m |
Footpath | Pour concrete on one side of road plus landscaping of remainder of footpath. | 1 small excavator, 1 truck, 6 workers to check levels, setup formwork and reinforcing, pour concrete, cure concrete | 900m |
Gabion retaining wall | Construct rock filled, wire gabion wall | 1 truck with small crane, 1 small backhoe to move rock fill, 4 workers to place rocks, and tie wire baskets together | 180m |
Landscaping | Landscaping of medians, footpaths and batter slopes. Spread topsoil, lay turf, and plant trees. | 1 front end loader to spread soil, 4 workers to lay turf and plant, water and fertilise trees. | 2600m |
Pavement marking | Paint line marking, place raised pavement markers | 1 line marking machine, 6 workers to set out and place pavement markers | 11000m |
Pedestrian fencing | Construct pedestrian fencing at back of footpath | 1 truck, 4 workers to pour footings and set up fence | 2600m |
Piers | Setup formwork, place reinforcement, pour concrete, cure concrete for piers | 1 crane, 1 barge, 1 pusher barge, 4 workers to check levels, setup bearings, set up formwork, pour and cure concrete | 2 piers |
Safety barriers (road) | Install posts for the safety barriers and connect the wire rope barriers | Backhoe with post borer, 1 truck, 4 workers to set out and attach barrier rails | 1700m |
Signposting | Pour footings, erect structures, mount signs | 1 truck with small crane, 1 small backhoe for excavation, 4 workers to pour footings, fix signs to structure | 5800m |
SO and SA kerb and gutter | Set out levels, place and compact base, pour and finish concrete gutter. | 1 Kerbmaker machine, 4 workers, 1 small compactor | 1800m |
Soft soil treatment at esatern abutment | Drill and insert steel tubes, fill with concrete, construct wharf | 1 Pile boring machine, 1 truck, 4 workers to check levels, place reinforcement, pour concrete. | 76 piles |
Sprayed bitumen sealing | Spray bitumen, spread aggregate, roll aggregate. | Specialist crew - sprayer, 4 trucks, rubber tyred roller 6 workers | 6000m |
Sub base pavement layer | Place and compact imported quarry subbase in one 300mm layer. Level accurately. | 1 grader, 1 water cart, 2 vibrating steel rollers, 1 rubber tyred roller,2 workers to check levels | 1100m |
Sub grade preparation | Accurately level the top of the excavation or top of fill. Compact to required density. | 1 grader, 1 water cart, 2 vibrating steel rollers, 1 rubber tyred roller, 2 workers to check levels | 1400m |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
SOLUTION Based on the information provided here are two possible production sequences for the road s...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started