Question
Consider projects A and B with the following cash flows: C 0 C 1 C 2 C 3 A $ 41 + $ 25 +
Consider projects A and B with the following cash flows: |
C0 | C1 | C2 | C3 | ||||||||||||||
A | $ | 41 | + | $ | 25 | + | $ | 25 | + | $ | 25 | ||||||
B | 66 | + | 35 | + | 35 | + | 35 | ||||||||||
a-1. | What is the NPV of each project if the discount rate is 12%? (Do not round intermediate calculations. Round your answers to 2 decimal places.) |
Project | NPV |
A | $ |
B | $ |
a-2. | Which project has the higher NPV? Project A or Project B |
b-1. | What is the profitability index of each project? (Do not round intermediate calculations. Round your answers to 2 decimal places.) |
Project | Profitability index |
A |
|
B |
|
b-2. | Which project has the higher profitability index? Project A or Project B |
c-1. | Which project is most attractive to a firm that can raise an unlimited amount of funds to pay for its investment projects? Project A or Project B |
c-2. | Which project is most attractive to a firm that is limited in the funds it can raise? Project A, Project B, or Both |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started