Question
1 Approved Answer
Consider projects Alpha and Beta: Cash Flows, $ Project C0. C1. C2 IRR (%) Alpha. 394,000 +257,000 +309,000 27 Beta. 195,000 +139,000 +180,000 38 The
Consider projects Alpha and Beta:
Cash Flows, $ Project C0. C1. C2 IRR (%) Alpha. 394,000 +257,000 +309,000 27 Beta. 195,000 +139,000 +180,000 38
The opportunity cost of capital is 8%.Suppose you can undertake Alpha or Beta, but not both.
a.
What is the NPV for each project?(Do not round intermediate calculations. Round your answers to 2 decimal places.)
ProjectNPV Alpha$ ? Beta$ ?
b.Which project did you choose?Beta/Alpha