Consider the following activity schedule for project Asimov for Questions 20-23: Slack CP Activity ? B C D E F ES 0 3 3 8
Consider the following activity schedule for project Asimov for Questions 20-23: Slack CP Activity ? B C D E F ES 0 3 3 8 8 12 EF 3 6 8 12 11 14 LS 0 5 3 8 9 12 LF 3 8 8 12 12 14 How many activities