Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Consider the following data for the project newt work that corresponds to the warehouse expansion case problem. Activity Optimistic Most Probable Pessimistic Imm. Predecessor A

Consider the following data for the project newt work that corresponds to the warehouse expansion case problem.
Activity
Optimistic
Most Probable
Pessimistic
Imm. Predecessor
A
4
6
8
-
B
6
8
16
-
C
2
4
6
A, B
D
8
10
24
C
E
7
10
13
C
F
4
6
8
E
G
4
6
20
C
H
4
6
8
D, F, G
I
4
6
14
D, F
J
3
4
5
H
K
2
4
6
I, J
Answer the following questions taking into consideration the additional information provided.
11
a. Develop the project newt work with activity scheduling (i.e., a table defining start time and finish time of each activity as well as the slack and the critical path). What is the expected project completion time? What is its corresponding variance? [8 Marks]
b. Determine the probability that the project can be completed in 40 weeks and 46 weeks? [4 Marks]
c. Using the expected activity times as the normal time and the following crashing activity information provided below. Determine the activity crashing decisions (activities, # of crashing day per activity, cost of crashing per crashed activity and the total cost) in order to reduce the expected project completion time by 5 weeks (i.e.,5 weeks less than the expected project completion time obtained in part a)[8 Marks]
Activity
Crashed Activity Time (Weeks)
Normal Cost
Crashed Cost
A
4
1,000
1,900
B
7
1,000
1,800
C
2
1,500
2,700
D
8
2,000
3,200
E
7
5,000
8,000
F
4
3,000
4,100
G
5
8,000
10,250
H
4
5,000
6,400
I
4
10,000
12,400
J
3
4,000
4,400
K
3
5,000
5,500

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Great Boss Great Management

Authors: S. M. H. Gibson

1st Edition

9798842893430

More Books

Students also viewed these General Management questions

Question

1. Follow directions the first time.

Answered: 1 week ago

Question

2. When is the job to be completed?

Answered: 1 week ago

Question

What are the steps involved in the HR planning process?

Answered: 1 week ago