Consider the following data for the project newt work that corresponds to the warehouse expansion case problem. Answer the following questions taking into consideration the

Consider the following data for the project newt work that corresponds
to the warehouse expansion case problem.
Answer the following questions taking into consideration the
additional information provided.
a. Develop the project newt work with activity scheduling (i.e., a
table defining start time and finish time of each activity as well as
the slack and the critical path). What is the expected project
completion time? What is its corresponding variance? [8 Marks]
b. Determine the probability that the project can be completed in 40
weeks and 46 weeks? [4 Marks]
c. Using the expected activity times as the normal time and the
following crashing activity information provided below. Determine the
activity crashing decisions (activities, # of crashing day per
activity, cost of crashing per crashed activity and the total cost) in
order to reduce the expected project completion time by 5 weeks (i.e.,
5 weeks less than the expected project completion time obtained in
part al)[8 Marks]
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Applied Wildlife Habitat Management

Authors: Roel R. Lopez, Michael L. Morrison, Israel D. Parker

1st Edition

9781623495022

More Books

Students also viewed these General Management questions

Question

The Functions of Language Problems with Language

Answered: 1 week ago