Consider the following data: Time Estimates ( days ) Activity Precedes Optimistic Most Likely Pessimistic table [ [ Start , A , B ,

Consider the following data:
Time Estimates (days)
Activity Precedes Optimistic Most Likely Pessimistic
\table[[Start,A,B,C,,-,-],[A,D,38,50,62],[B,E,90,99,108],[C,End,185,100,115],[D,F,19,25,37],[E,End,91,100,115],[F,End,62,65,68]]
For activity D, what are the estimated expected (mean) time (te) and variance?
25 days and 18 days
116.67 days and 24 days
81 days and 3 days
26 days and 9 days
133.33 days and 2 days respectively
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management A Practical Introduction

Authors: Angelo Kinicki, Brian Williams

5th edition

978-1111821227, 9781133190363, 1111821224, 1133190367, 978-0078112713

More Books