Consider the following information: Demand rate (D)= 310 units per hour Lead time (T)= 8 hours Container capacity (C)=30 units Safety factor (x)= 15% a.

image text in transcribed

Consider the following information:

Demand rate (D)= 310 units per hour

Lead time (T)= 8 hours

Container capacity (C)=30 units

Safety factor (x)= 15%

a. the number of kanban production cards is___.

b. The cards will represent ___ hours' worth of demand.

c. Suppose the lead time is reduced to seven hours. The number of Kanban production cards is___.

The cards will represent__ hours' worth of demand.

Consider the following information: Demand rate (D)=310 units per hour Lead time (T)=8 hours Container capacity (C)=30 units Safety factor (x)=15% a. The number of kanban production cards is (Enter your response rounded up to the next whole number.) b. The cards will represent hours' worth of demand. (Enter your response rounded to one decimal place.) c. Suppose the lead time is reduced to seven hours. The number of kanban production cards is (Enter your response rounded up to the next whole number.) The cards will represent hours' worth of demand. (Enter your response rounded to one decimal place.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Great Boss Great Management

Authors: S. M. H. Gibson

1st Edition

9798842893430

More Books

Students also viewed these General Management questions

Question

16.7 Describe the three steps in the collective bargaining process.

Answered: 1 week ago