Consider the following information: Demand rate (D)= 310 units per hour Lead time (T)= 8 hours Container capacity (C)=30 units Safety factor (x)= 15% a.
Consider the following information:
Demand rate (D)= 310 units per hour
Lead time (T)= 8 hours
Container capacity (C)=30 units
Safety factor (x)= 15%
a. the number of kanban production cards is___.
b. The cards will represent ___ hours' worth of demand.
c. Suppose the lead time is reduced to seven hours. The number of Kanban production cards is___.
The cards will represent__ hours' worth of demand.
Consider the following information: Demand rate (D)=310 units per hour Lead time (T)=8 hours Container capacity (C)=30 units Safety factor (x)=15% a. The number of kanban production cards is (Enter your response rounded up to the next whole number.) b. The cards will represent hours' worth of demand. (Enter your response rounded to one decimal place.) c. Suppose the lead time is reduced to seven hours. The number of kanban production cards is (Enter your response rounded up to the next whole number.) The cards will represent hours' worth of demand. (Enter your response rounded to one decimal place.)Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started