Question
Consider the following master schedule record. Now suppose the lead time for item A2 is fourweeks rather than oneweek. Based on this information, can the
Consider the following master schedule record. Now suppose the lead time for item A2 is
fourweeks
rather than
oneweek.
Based on this information, can the company support the current gross requirements for the A2? What are the implications of having reliable supplier and manufacturing lead times in an MRP environment?
Click the icon to view the MRP record.Part 2Calculate the material requirements plan (enter your responses as whole numbers and include a minus sign if necessary).
Week | 1 | 2 | 3 | 4 | 5 | 6 | |
***A2*** | Gross requirements | 0 | 400 | 400 | 350 | 500 | 350 |
LT(weeks)=4 | Scheduled receipts | 380 | |||||
Projected ending inventory: 70 | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | |
Net requirements | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | |
Min. order=1 | Planned receipts | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started