Consider the following project activities: Activity Name Immediate Predecessor (list number/ name, separated by ,) Normal Time A 6 B A 2 C A 4
Consider the following project activities:
Activity Name | Immediate Predecessor (list number/ name, separated by ,) | Normal Time |
A |
| 6 |
B | A | 2 |
C | A | 4 |
D | B, C | 3 |
E | D | 1 |
F | D | 7 |
G | E | 4 |
H | F, G | 2 |
I | F | 6 |
J | I | 1 |
K | H, J | 5 |
Fill the following table:
Activity Name
| Activity Time | Earliest Start | Earliest Finish | Latest Start | Latest Finish | Slack (LS-ES) |
A | 6 |
|
|
|
|
|
B | 2 |
|
|
|
|
|
C | 4 |
|
|
|
|
|
D | 3 |
|
|
|
|
|
E | 1 |
|
|
|
|
|
F | 7 |
|
|
|
|
|
G | 4 |
|
|
|
|
|
H | 2 |
|
|
|
|
|
I | 6 |
|
|
|
|
|
J | 1 |
|
|
|
|
|
K | 5 |
|
|
|
|
|
Project Completion Time = |
| Days | ||||
The Critical Path is= |
|
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started