Question: Consider the following project activities: Activity Name Immediate Predecessor (list number/ name, separated by ,) Normal Time A 6 B A 2 C A 4

Consider the following project activities:

Activity Name

Immediate Predecessor (list number/ name, separated by ,)

Normal Time

A

6

B

A

2

C

A

4

D

B, C

3

E

D

1

F

D

7

G

E

4

H

F, G

2

I

F

6

J

I

1

K

H, J

5

Fill the following table:

Activity Name

Activity Time

Earliest

Start

Earliest

Finish

Latest Start

Latest Finish

Slack

(LS-ES)

A

6

B

2

C

4

D

3

E

1

F

7

G

4

H

2

I

6

J

1

K

5

Project Completion Time =

Days

The Critical Path is=

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!