Consider the following project activities and determine the resource peak. All activities are connected through FS relationships with no lead or lag. What is the original project duration (just based on CPM; ignoring resource constraints)? The CPM based project duration is days. What's the maximum number of labourer units you require for this project accordina to the original schedule abov The maximum number of labourer units required for this project is %. Next consider this limitation: All activities are performed in the same work area; however, only a maximum of 2000 Resolve the resource overallocation following the Least Slack rule (also known as "The Minimum Slack Rule"). (AC Make sure you show your calculation steps and explain your reasoning in the solution file that you submit in the col Caleulate the reuiltinn Farly Start dates for the activities and enter them below. What is the new project duration. once the resource overallocation has been resolved? The new project duration is days 2000% labourer units are allowed in the area. This means the original schedule above will not be feasible. le"). (Activities with the most slack are pushed out first.) n the context of this assignment. Consider the following project activities and determine the resource peak. All activities are connected through FS relationships with no lead or lag. What is the original project duration (just based on CPM; ignoring resource constraints)? The CPM based project duration is days. What's the maximum number of labourer units you require for this project accordina to the original schedule abov The maximum number of labourer units required for this project is %. Next consider this limitation: All activities are performed in the same work area; however, only a maximum of 2000 Resolve the resource overallocation following the Least Slack rule (also known as "The Minimum Slack Rule"). (AC Make sure you show your calculation steps and explain your reasoning in the solution file that you submit in the col Caleulate the reuiltinn Farly Start dates for the activities and enter them below. What is the new project duration. once the resource overallocation has been resolved? The new project duration is days 2000% labourer units are allowed in the area. This means the original schedule above will not be feasible. le"). (Activities with the most slack are pushed out first.) n the context of this assignment