Consider the following project: Activity Immeadiate Predecessors Durations (weeks) A 6 B A 3 C A 2 D B 3 E C 8 F
Consider the following project: Activity Immeadiate Predecessors Durations (weeks) A 6 B A 3 C A 2 D B 3 E C 8 F B.C 3 G D, E 7 H C 2 What is the latest start time for activity G?