Consider the following project: Activity Time Predecessor A 1 2 - B 1 0 - C 9 A D 1 5 A E 7 B

Consider the following project:
Activity Time Predecessor
A 12-
B 10-
C 9 A
D 15 A
E 7 B
F 8 D, E
G 13 C, F
What is the slack time for the activity C?
Group of answer choices
None of the above answers is correct.
14
8
0
10