Consider the following project. If the project extends beyond 42 days, a lumpsum penalty of $25000 needs to be paid. What is the expected
Consider the following project. If the project extends beyond 42 days, a lumpsum penalty of $25000 needs to be paid. What is the expected penalty? Round to 2 decimals for all calculations. Path Expected Paths Variancesduration A-B-C- 6.4 43 D E-F-G-H 4.9 I-J-K-L 2.5 33 34 30