Consider the following project information: Activity Immediate Predecessors Optimistic Time (o) Most likely Time (m) Pessimistic Time (p) A none 4 7 9 B none

Consider the following project information:

Activity Immediate Predecessors Optimistic Time (o) Most likely Time (m) Pessimistic Time (p)
A none 4 7 9
B none 3 5 8
C A 2 4 6
D A, B 6 9 9
E C, D 5 5 5
F B 2 5 9
G E, F 3 3 6


1. What is the expected project completion time?

2. What is the standard deviation of the critical path's time?

3. What is the probability that the project will be completed in 25 weeks?

Step by Step Solution

3.42 Rating (152 Votes )

There are 3 Steps involved in it

Step: 1

1 The expected time of an activity Optimistic time 4most likely time Pessimist... blur-text-image
Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction to Operations Research

Authors: Frederick S. Hillier, Gerald J. Lieberman

10th edition

978-0072535105, 72535105, 978-1259162985

More Books

Students explore these related General Management questions