Consider the following project network and activity times ( in days ) . Assume that management desires a 1 2 - day project completion time.

Consider the following project network and activity times (in days). Assume that management desires a 12-day project completion time.
A project network is given with the starting point on the left and the ending finish point on the right with activities A through G. The arcs between the activities are listed as follows.
Start to A and B
A to C
B to D
C to E and F
D to E and F
F to G
E and G to Finish
Activity A B C D E F G
Time 3255622
The crashing data for this project are as follows.
Time (days) Cost ($)
Activity Normal Crash Normal Crash
A 328001,400
B 211,2001,900
C 532,0002,800
D 531,5002,300
E 641,8002,800
F 216001,000
G 215001,000
(a)
Formulate a linear programming model that can be used to assist with the crashing decisions. (The objective function should be the additional cost of crashing. Let
xi =
the finish time for activity i and
yi =
the amount of time activity i is crashed where i = A, B, C, D, E, F, and G. Let
xFIN =
the finish time for the entire project.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management

Authors: Jay Heizer, Barry Render

11th edition

9780132921145, 132921146, 978-0133408010

More Books

Students also viewed these General Management questions