Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Consider the following project. Normal Crashing Activity 1 st Crashing Activity 2nd Time Time Activ Predecessor Direct Duration Additional Duration Additional Duration ity Cost (Week)

image text in transcribed
Consider the following project. Normal Crashing Activity 1 st Crashing Activity 2nd Time Time Activ Predecessor Direct Duration Additional Duration Additional Duration ity Cost (Week) Direct Cost (Week) Direct Cost (Week) A $200,000 5 $10,000 4 $10,000 3 B A $50,000 6 $15,000 5 $15,000 4 C A $250,000 $5,000 3 $5,000 2 D A $100,000 5 $15,000 $15,000 3 E B $25,000 9 $15,000 8 $15,000 7 B. C $75,000 7 $7,500 $7,500 5 G C $125,000 6 $10,000 5 $10,000 4 H C, D $100,000 8 $15,000 7 $15,000 6 D $20,000 3 $10,000 2 $10,000 E, F, G $75,000 7 $2,500 6 $2,500 5 K F, G, H $50,000 4 $10,000 3 $10,000 2 L H, I $20,000 M K, L $25,000 2 $25,000 a) Develop the project cash flow and S-curve diagrams for the early and late start durations before any of the activities are crashed. For this part of the problem. You can use Excel to develop these curves, if you like. (33 points) b) Crash the project to the least possible duration. Make sure to record the total direct cost and duration for each iteration. (34 points) c) Assume the project overhead is 10% of the total direct cost. The owner wants the project to be completed in 24 weeks or less and will charge a penalty of $10,000 for each week of delay beyond 24 weeks. Determine the optimum project duration and total price. (33 points)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management An Integrated Approach

Authors: R. Dan Reid, Nada R. Sanders

7th Edition

1119497388, 978-1119497387

More Books

Students also viewed these General Management questions