Consider the following project where times are in weeks. Activity Immediate Predecessors Duration A - 8 B - 12 C A,B 7 D B 4
Consider the following project where times are in weeks.
Activity | Immediate Predecessors | Duration |
A | - | 8 |
B | - | 12 |
C | A,B | 7 |
D | B | 4 |
AND | A | 2 |
F | C | 3 |
G | E,F | 7 |
H | D,F | 3 |
what is the early start for activity B using the same-day method?