Consider the following project, which consists of ten tasks : Task Completion (Days) Immediate Predecessors A 6 None B 2 None C 3 A D
- Consider the following project, which consists of ten tasks :
Task | Completion (Days) | Immediate Predecessors |
A | 6 | None |
B | 2 | None |
C | 3 | A |
D | 5 | A |
E | 3 | A |
F | 2 | C |
G | 3 | E |
H | 4 | B, E |
I | 2 | H |
J | 2 | F, G, I |
a. What is the critical path through this network? What is the completion time of this project?
b. What is the slack in Task F?
c. Suppose the project has just been started. What is the longest you could delay beginning work on Activity A, without delaying the completion of the project?
d. Suppose someone tells you they could get activity C done in 1 day, instead of the 3 days you were planning on. Of course, they expect a bonus for this. What is your reaction?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started