Consider the following project: Year 0 1 2 3 Cash flow -$21.00 $7.00 $11.00 $15.00 What is the NPV of this project if the cost

Consider the following project:

Year 0 1 2 3
Cash flow -$21.00 $7.00 $11.00 $15.00

What is the NPV of this project if the cost of capital is 12.00%?

A project requires an initial investment today of $100,163.00. The project will last three years. However, the company believes that the risk involved with the project will increase over its life, so they would like a greater return for later cash flows. The table below shows the projected cash flows and the discount rates required for the project.

Year 0 1 2 3
Cash flow -$100,163.00 $54,089.00 $49,814.00 $45,188.00
Discount rate 9.00% 13.00% 18.00%

What is the NPV of this project?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Markets And Institutions

Authors: Jeff Madura

13th Edition

0357130790, 978-0357130797

More Books

Students also viewed these Finance questions

Question

Define self-esteem and discuss its impact on your life.

Answered: 1 week ago