Consider the following set of processes that arrive at time 0, with the length of the CPU burst (burst time) given in milliseconds: Process Burst

Consider the following set of processes that arrive at time 0, with the length of the CPU burst (burst time) given in milliseconds:

Process Burst Time P1 24

P2 3

P3 3

If the processes arrive in the order P1, P2, P3, and are served in First-Come-First-Served scheduling order, what is the average turnaround time (in milliseconds)?

(Note: The turnaround time measures how long the average user has to wait for the output.)

(Hint: If process X is scheduled before process Y, then Y needs to wait until X is completed.)

24

10

27

13

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Visual C# And Databases

Authors: Philip Conrod, Lou Tylee

16th Edition

1951077083, 978-1951077082

More Books

Students also viewed these Databases questions

Question

Distinguish between hearing and listening.

Answered: 1 week ago

Question

Use your voice effectively.

Answered: 1 week ago