Consider the following set of processes, with the length of the CPU burst and arrival time given in seconds: Process Arrival Time Burst Time P2

Consider the following set of processes, with the length of the CPU burst and arrival time given in seconds:

Process
Arrival Time
Burst Time
P2
0
12
P3
3
8
P4
5
4
P1
10
10
P5
12
6


  • Draw Gantt chart that illustrate the execution of these processes using theShortest Remaining Job First (SJRF) a.k.a preemptive Shortest Job First.
  • What is the turnaround time of each process?
  • What is the waiting time of each process?
  • What is the Averageturnaround time of the execution?
  •  What is the Averagewaiting time of the execution?

Step by Step Solution

3.42 Rating (168 Votes )

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Value at Risk The New Benchmark for Managing Financial Risk

Authors: Philippe Jorion

3rd edition

0070700427, 71464956, 978-0071464956

More Books

Students also viewed these Operating System questions