Consider the following statement: Sometimes, it may be more cost - effective to accept and manage a certain level of risk, even if other risk

Consider the following statement:
"Sometimes, it may be more cost-effective to accept and manage a certain level of risk, even if other risk management methods are available, based on the likelihood and severity of the risks involved. "
This correspond to which risk treatment technique?
Select one:
a.
Spreading / Sharing
b.
Loss prevention and reduction
c.
Retention and Acceptance
d.
Transfer
e.
Avoidance / Elimination

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Natural Resource Management Reimagined

Authors: Robert G. Woodmansee

1st Edition

1108740138, 978-1108740135

More Books

Students also viewed these General Management questions

Question

Why could the Robert Bosch approach make sense to the company?

Answered: 1 week ago