Consider the following table: ACTIVITY PREC. ACT. TIME ESTIMATES (days) t o t ml t p t e A ----- 1 2 3 B A
Consider the following table:
ACTIVITY PREC. ACT. TIME ESTIMATES (days)
to tml tp te
A ----- 1 2 3
B A 2 4 6
C B 1 4 7
D B 3 4 5
E C 1 3 5
F D, E 2 3 4
1) Construct a PERT network.
[NOTE: This is the most crucial part of the exercise. Make sure you have the correct network before proceeding to the next sections.]
2) By using ES, EF, LF, LS, find the slack of each activity and the critical path.
3) Find the completion time and the standard deviation () for the project round off the standard deviation to the nearest hundredth: two decimal places.
4) What is the completion time at 95% confidence level?
5) What is the likelihood of this project being completed earlier than 14 days?
6) Between 13 and 15 days?
Consider the following table:
ACTIVITY PREC. ACT. TIME ESTIMATES (days)
to tml tp te
A ----- 1 2 3
B A 2 4 6
C B 1 4 7
D B 3 4 5
E C 1 3 5
F D, E 2 3 4
1) Construct a PERT network.
[NOTE: This is the most crucial part of the exercise. Make sure you have the correct network before proceeding to the next sections.]
2) By using ES, EF, LF, LS, find the slack of each activity and the critical path.
3) Find the completion time and the standard deviation () for the project round off the standard deviation to the nearest hundredth: two decimal places.
4) What is the completion time at 95% confidence level?
5) What is the likelihood of this project being completed earlier than 14 days?
6) Between 13 and 15 days?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access with AI-Powered Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started