Consider the following table below and answer the following questions. 1. Conduct both a forward and backward pass using AON notation. What is the estimated
Consider the following table below and answer the following questions.
1. Conduct both a forward and backward pass using AON notation. What is the estimated total duration for the project? 2. Identify all paths through the network. Which is the critical path? 3. Which activities have slack time? 4. Identify all burst activities and merge activities.
Question 2
Consider the following table and find the Critical path for the project.
\begin{tabular}{|c|c|c|c|} \hline Activity & Description & Predecessors & Duration (Days) \\ \hline A & Site selection & None & 4 \\ \hline B & Buy concessions & A & 4 \\ \hline C & Rent facilities & A & 2 \\ \hline D & Build stands & A & 5 \\ \hline E & Generator \& wiring installation & C & 2 \\ \hline F & Security & B & 4 \\ \hline G & Lighting installation & E & 2 \\ \hline H & Sound system installation & E,F & 2 \\ \hline I & Stage construction & D & 3 \\ \hline J & Tear down & G,H,I & 4 \\ \hline \end{tabular} \begin{tabular}{|c|c|c|} \hline Activity & Duration & Predecessors \\ \hline A & 3 & - \\ \hline B & 5 & A \\ \hline C & 7 & \\ \hline D & 3 & B, C \\ \hline E & 5 & B \\ \hline F & 4 & D \\ \hline G & 2 & C \\ \hline H & 5 & \\ \hline \end{tabular}Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started