Consider the following table of activities A through E in which A is the start node and E is the stop node. Assume the project
Consider the following table of activities A through E in which A is the start node and E is the stop node. Assume the project starts on Monday, May and no work is done on weekends Saturday and Sunday
Project Activities
Activity
Duration days
Predecessor
A
B
A
C
A
D
A
E
B C D
On a piece of scratch paper, draw the Gantt Chart for the table above. What is the late start date for activity E