Consider the following table of activities A through G in which A is the start node and G is the stop node. Activity Duration
Consider the following table of activities A through G in which A is the start node and G is the stop node. Activity Duration (days) 10 Predecessor A B 20 A C 5 A D 3 B, C E 20 B. C F 4 B, C G 10 D, E, F On a piece of scratch paper, draw the network associated with this table and determine the following. What is the late finish time for activity G?