Consider the following table of activities A through G in which A is the start node and G is the stop node. table [
Consider the following table of activities A through in which is the start node and is the stop node.
tableActivityDuration daysPredecessorABACADAEB C DFB C DGE F
On a piece of scratch paper, draw the network associated with this table and determine the following. Suppose activity were to slip by two days, taking its duration from six to eight days. What would be the effect on overall project duration?