Consider the following table of activities A through G in which A is the start node and G is the stop node. Activity Duration (days)

Consider the following table of activities A through G in which A is the start node and G is the stop node.

Activity Duration (days) Predecessor
A 5 --
B 8 A
C 7 A
D 6 A
E 9 B, C, D
F 10 B, C, D
G 5 E, F

On a piece of scratch paper, draw the network associated with this table and determine the following. Considering the lengths of all the paths, which of these paths is shortest and what is its length?

Question 6 options:

a A-B-F-G, 28
b A-D-E-G, 25
c A-D-E-G, 20
d A-C-E-G, 28
e A-C-E-G. 26

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The ABCs Of Property Management

Authors: Ken McElroy

1st Edition

9781937832537

More Books

Students also viewed these General Management questions

Question

HC accounts are neither objective nor useful. Discuss.

Answered: 1 week ago

Question

Q: What is the role of the Barika store?

Answered: 1 week ago